As part of the South Terminal Exit Roadways Improvement
project at Fort Lauderdale-Hollywood International Airport,
BPA recently completed the structural design and
construction inspection services for the New Toll
Plaza /Administration Building facility and Mechanical Room. BPA is proud to have participated in the Team that helped
implement this $9 M toll plaza relocation in record time.
Our role during the fast track design process included the
structural design of the toll plaza canopy structure and the
Administration Building located on the ground level of the
Hibiscus Parking Garage. Once the design phase was
completed, BPA served as special inspector providing
construction inspection services for the structural
components, including shop drawing approval and responding
to RFIs. |